The Virginia Pulse
Virginia data centers

The Data Center Download

Virginia is home to the world's largest data center market. Here's every data center project, vote and local rule The Virginia Pulse is tracking, updated daily. Updated November 17, 2026.

Local rules · Map · Vote Watch · Projects · Stories · 2027 Watch

Where the rules stand

LOUDOUN COUNTY

Pause pending. Supervisors voted on Sept. 15, 2026 to advance a pause on legislative data center and substation applications. The formal resolution, which would pause those applications for up to 12 months, was deferred on Oct. 20 to the board's Nov. 17, 2026 meeting.

Source: Loudoun County notice, Oct. 20, 2026 · Loudoun County release, Sept. 16, 2026
PRINCE WILLIAM COUNTY

Tightened. On Sept. 22, 2026 the Board of County Supervisors adopted Ordinance 26-67, which reduces and redefines the Data Center Opportunity Zone Overlay District and closes it to expansion. Pending applications have until Dec. 21, 2026, 90 days after adoption, to qualify. New data center proposals in the listed commercial, office and industrial districts need a special use permit.

Source: Prince William County Planning Office, DPA2026-00006
CHESTERFIELD COUNTY

Closed to new projects. The Board of Supervisors indicated in August 2026 that it won't approve any more data center projects.

Source (news report)
HENRICO COUNTY

Restricted. Henrico ended by-right approvals for data centers in June 2025, so new projects need county approval through public hearings. The county is steering its industrial land toward pharmaceutical and advanced manufacturing.

Source (news report)
DANVILLE

Newly open. City Council voted unanimously in May 2026 to allow data centers on sites over 150 acres, at least 500 feet from homes and outside industrial parks. The data center equipment tax rose to $1.20 per $100 on July 1, 2026.

Source (news report)
APPOMATTOX COUNTY

By right. Data centers are allowed on the county's industrial-zoned land, so the $3 billion Project Hercules campus needs no rezoning or public hearing.

Source (news report)
STATEWIDE

New rules coming. On Sept. 18, 2026 Gov. Spanberger presented a Data Center Accountability Framework, including a ban on non-disclosure agreements for commercial data center projects, local approval for facilities above 25 megawatts and a larger share of energy costs for data centers. She plans to work with the General Assembly to put it into law in the 2027 session. A state law requires data centers to report water use starting in 2027.

Source: Governor of Virginia, Sept. 18, 2026 · Source for water-use reporting: Virginia Mercury (news report)

Where it's happening

Counties and cities with tracked data center projects or votes. Darker means more. Select one for its page. See all localities.

Data center Vote Watch

NOV 17
Loudoun County · Vote

Data center application pause

Board of Supervisors final vote on 12-month data center and substation application pause (deferred from Oct. 20)

Source

NOV 17
Spotsylvania County

Crossroads Technology Campus data center

Board of Supervisors public hearing and vote on data center special use permit SUP26-0003 (hearing 5:45 p.m., Holbert Building)

Source

NOV 18
Chesterfield County · Policy

Chesterfield data center car tax ordinance

Board of Supervisors consideration of data center revenue car tax ordinance (deferred Aug. 26 and Sept. 23)

Source

NOV 18
Stafford County

Kings Highway (Route 3) data center sites

Planning Commission public hearings and recommendations on Forest Lane, Simms Farm, Sisson North and Sisson South (moved from Oct. 14)

Source

DEC 2
Fairfax County

Plaza 500 data center and Edsall Road substation

Planning Commission 2232 public hearing on Dominion's Edsall Road substation, 7:30 p.m.

Source

DEC 21
Prince William County · Policy

Data center overlay reduction

Final eligibility period closes for data center overlay (90 days after adoption); county to publish updated boundary map afterward

Source

JAN 16
Statewide · Policy

Executive Order 22 data center directives

Initial data center Planning and Community Engagement Toolkit due (120 days after Sept. 18 signing)

Source

Recent decisions

OCT 28
Frederick County

Winchester Gateway data center campus

Denied unanimously by Board of Supervisors Oct. 28, 2026

Source

OCT 27
Fairfax County · Policy

Fairfax data center state-coordination directive

Board unanimously directed staff Oct. 27, 2026, to coordinate with the state on data center rules; report due in 120 days

Source

OCT 26
Frederick County

Virginia Technology Park data center campus

Applicant withdrew the rezoning request Oct. 26, 2026

Source

OCT 23
Loudoun County · Policy

Loudoun data center (high energy use facility) application requirements

Loudoun began requiring the new data center application documents, announced Oct. 23, 2026

Source

OCT 21
Suffolk · Policy

Suffolk temporary data center ban

Adopted unanimously Oct. 21, 2026

Source

OCT 20
Loudoun County · Vote

Data center application pause

Deferred Oct. 20, 2026, to Nov. 17 at the county attorney's request

Source

OCT 20
Goochland County · Vote

Goochland Technology Overlay District lawsuit (data center zoning)

Judge took county's motion to dismiss under advisement Oct. 20, 2026; no ruling yet

Source

OCT 20
Loudoun County

Bridgefield Tech Center (former GW Ashburn campus)

Amazon agreed Oct. 20, 2026, to withdraw its 800,000-sq-ft data center plan; site to be rezoned for mixed use

Source

Data center projects

ProjectRegionValueStatusWhat's next
Pittsylvania County
Southside$100BApprovedState (DEQ) and Army Corps permit review; 150 MW substation expected by 2028
Appomattox County
Central Virginia$3BApprovedConstruction expected to start by end of 2026; initial power 2027
Botetourt County
Southwest Virginia$3BProposedCircuit Court hearing on FOIA suit (date not set); Army Corps permit decision (no date); DEQ reviewing water protection and air permits
Pulaski County
Southwest Virginia$750MProposedAuthority assessing other options; no new developer identified
Spotsylvania County
Northern VirginiaNot disclosedProposedRezoning case R25-0014 pending; no hearing date posted
Chesterfield County
RichmondNot disclosedUnder constructionOct. 29 DEQ response deadline has passed; no published outcome found as of Nov. 10
Roanoke County
Southwest VirginiaNot disclosedProposedGoogle due diligence expected through March 2027
Frederick County
Shenandoah ValleyNot disclosedProposedRezoning request withdrawn Oct. 26; no hearing scheduled
Fairfax County
Northern VirginiaNot disclosedVote pendingDec. 2: Planning Commission 2232 public hearing on Dominion's Edsall Road substation, 7:30 p.m.
Spotsylvania County
Northern VirginiaNot disclosedVote pendingNov. 17: Board of Supervisors public hearing and vote on data center special use permit SUP26-0003 (hearing 5:45 p.m., Holbert Building)
Goochland County
RichmondNot disclosedProposedGoogle decision on purchase and site plan; by-right in Technology Overlay District per BizSense, no public hearing
Frederick County
Shenandoah ValleyNot disclosedProposedDenied; no further hearing scheduled. Data centers no longer a permitted or conditional use in Frederick County
Russell County
Southwest VirginiaNot disclosedProposedDeveloper-hosted community forum Nov. 18, Russell County government center (no vote); IDA meeting in November
Fairfax County
Northern VirginiaNot disclosedProposedFairfax County special exception review; no hearing scheduled
Stafford County
Northern VirginiaNot disclosedVote pendingNov. 18: Planning Commission public hearings and recommendations on Forest Lane, Simms Farm, Sisson North and Sisson South (moved from Oct. 14)
Carroll County
Southwest VirginiaNot disclosedProposedCarroll supervisors weighing whether to give the regional authority final approval on the data center (no vote date)
Stafford County
Northern VirginiaNot disclosedApprovedSite plan review; no dates announced
Appomattox County
Central VirginiaNot disclosedProposedDominion community meeting on routes was set for Nov. 5 (outcome not reported); final route and state approval still needed (no dates set)

Data center stories

WYTHE COUNTYNovember 17, 2026

Wythe zoning draft would shield data centers with county permits

Wythe County's draft Land Use Classification Ordinance would treat projects holding certain county permits as lawful, and a Board of Supervisors hearing is tentatively set for Dec. 3.

Read the story →
CHESTERFIELD COUNTYNovember 16, 2026

Chesterfield returns Nov. 18 to data center car tax cut

Chesterfield's Board of Supervisors takes up, for the third time, an ordinance sending all data center tax revenue toward lower car taxes.

Read the story →
STATEWIDENovember 14, 2026

Data center tax exemption is 60% of Virginia incentive spending

JLARC's 2026 incentives report puts the data center sales tax exemption at about $4.06 billion of $6.8 billion in incentive spending since fiscal 2016.

Read the story →
SPOTSYLVANIA COUNTYNovember 13, 2026

Spotsylvania has approved 15.5 million sq ft of data centers

The county's own August figures show 1,104 industrial acres left under a proposed 45% cap, and its page still lists the cap as a draft.

Read the story →
SMYTH COUNTYNovember 12, 2026

Smyth County resident sues to void data center ordinance

A county resident has asked Smyth County Circuit Court to void the supervisors' vote on a zoning ordinance that requires special use permits for data centers.

Read the story →
STAFFORD COUNTYNovember 11, 2026

Stafford's Route 3 data center plan: 1,405 acres, 14 substations

Stafford's Planning Commission holds one Nov. 18 public hearing on four linked Kings Highway data center applications covering 1,404.82 acres and about 9 million square feet.

Read the story →
SPOTSYLVANIA COUNTYNovember 10, 2026

Spotsylvania to vote Nov. 17 on 555-acre Crossroads data center campus

Spotsylvania supervisors are set to hold a public hearing and vote Nov. 17 on a special use permit for a 2.1 million-square-foot data center campus.

Read the story →
PRINCE WILLIAM COUNTYNovember 9, 2026

Prince William's data center overlay closes to new entrants Dec. 21

Pending data center applications have until Dec. 21 to qualify for the county's shrunken by-right overlay; a county staff analysis counted 130 parcels relying on that last window.

Read the story →
VIRGINIANovember 7, 2026

Virginia's data center tax break cost $1.94B last year, and voters oppose it

The data center sales tax exemption cost Virginia and localities a reported $1.94 billion in fiscal 2025, and a VCU poll found 72% of voters oppose it. The 2027 General Assembly and county boards decide what changes.

Read the story →
STATEWIDENovember 7, 2026

Governor's data center order sets deadlines starting in January

Executive Order 22 gives state agencies 120 to 240 days from Sept. 18 to deliver a toolkit for localities, noise rules and a backup-generator review.

Read the story →
STATEWIDENovember 6, 2026

Dominion's data center pipeline reaches 54.9 GW, up 13% this year

Dominion Energy reported 54.9 gigawatts of data center capacity in various stages of contracting as of September, with more than 12 GW under signed electric service agreements.

Read the story →
LOUDOUN AND FREDERICK COUNTIESNovember 5, 2026

Valley North power line open houses reach Winchester and Lovettsville

Valley Link holds drop-in open houses in Winchester on Nov. 5 and Lovettsville on Nov. 12 on its proposed 260-mile, 765-kilovolt Valley North line.

Read the story →
BOTETOURT COUNTYNovember 4, 2026

Resident sues to void Botetourt's Google data center agreement

A Botetourt resident filed suit Nov. 2 claiming the county broke the state open-records law when it approved its $1 billion-per-building agreement with Google in 2025.

Read the story →
FREDERICK COUNTYNovember 3, 2026

Frederick denies 72-acre Winchester Gateway data center

Frederick County supervisors voted unanimously Oct. 28 to deny a conditional-use permit for a 72-acre, three-building data center campus in Kernstown.

Read the story →
GOOCHLAND COUNTYOctober 31, 2026

Google weighs 1,200-MW data center campus at Goochland's West Creek

Google confirmed it is doing due diligence on a roughly 1,000-acre West Creek Business Park site, where a data center could proceed by right with no public hearing.

Read the story →
BOTETOURT COUNTYOctober 30, 2026

Corps skips public hearing on Google's Botetourt data center campus

The U.S. Army Corps of Engineers will not hold a public hearing on Google's three-building data center plan despite 282 requests.

Read the story →
FREDERICK COUNTYOctober 29, 2026

Developer pulls 220-acre Frederick County data center rezoning

Equus Capital Partners withdrew its Virginia Technology Park rezoning request in Clear Brook two days before a county board hearing.

Read the story →
CARROLL COUNTYOctober 28, 2026

Carroll holds the key to an $11B Wildwood data center plan

A planned data center at Wildwood Commerce Park, expected to bring more than $11 billion in investment, is stalled because Carroll County has not signed on to a plan to let a regional authority make the final call.

Read the story →
SPOTSYLVANIA COUNTYOctober 27, 2026

Spotsylvania votes tonight on plan capping data center land at 45%

Spotsylvania supervisors are scheduled to vote Oct. 27 on an updated Comprehensive Plan that recommends data centers take up no more than 45% of the county's industrial-zoned land.

Read the story →
LOUDOUN COUNTYOctober 26, 2026

Amazon drops 800,000-sq-ft data center plan at former GW campus

Amazon will withdraw its Ashburn data center application, donate 25 acres and $5 million for housing, and let Loudoun rezone the former George Washington University campus with a data center ban.

Read the story →
LOUDOUN COUNTYOctober 21, 2026

Loudoun pushes data center pause vote to Nov. 17

Loudoun supervisors delayed their final vote on a 12-month pause on data center and substation applications from Oct. 20 to Nov. 17 after the county attorney asked for more time.

Read the story →
PITTSYLVANIA COUNTYOctober 20, 2026

Berry Hill data center permit shows 3,000 MW, 7M gallons a day

A state and federal permit application for Stack Infrastructure's AI data center campus at the Berry Hill megasite lays out 21 buildings, up to 3,000 megawatts of power and up to 7 million gallons of water a day.

Read the story →
CHESTERFIELD COUNTYOctober 13, 2026

Chesterfield appeals board rejects by-right data center claim

Chesterfield's Board of Zoning Appeals voted 4-0 to uphold a ruling that WestDulles Properties needs a conditional use permit for a data center campus on a 550-acre site near Chester.

Read the story →
PULASKI COUNTYOctober 12, 2026

Buyer walks away from $750M New River Valley Commerce Park deal

A company that proposed $750 million in industrial development, including a data center, on 475 acres in Pulaski County let its purchase contract expire after missing an Oct. 5 closing.

Read the story →
STAFFORD COUNTYOctober 11, 2026

Stafford approves Accokeek data center, larger Route 3 sites up next

Stafford supervisors approved a 590,000-square-foot data center campus 4-3, and the Planning Commission takes up four much larger Kings Highway sites on Oct. 14.

Read the story →
CAMPBELL COUNTYOctober 9, 2026

Campbell County joins opposition to $1B Valley Link power line

Campbell County supervisors voted 4-3 on Oct. 6 to oppose the Joshua Falls-Yeat line, a $1 billion, 765-kilovolt project that would run about 115 miles to Culpeper County.

Read the story →
LOUDOUN COUNTYOctober 7, 2026

Loudoun shelves plan to end data center grandfathering

After the county attorney warned of up to $60 million in litigation risk, Loudoun supervisors tabled a proposal to strip grandfathered status from pending data center applications.

Read the story →
APPOMATTOX COUNTYOctober 6, 2026

$3 billion data center campus set to break ground in Appomattox

AVAIO Digital Partners expects to start building its Project Hercules data center campus in Appomattox County by the end of 2026.

Read the story →
NORTHERN VIRGINIAOctober 5, 2026

Northern Virginia hits the brakes on data centers

Loudoun and Prince William, home to the world's largest data center market, are both making new projects harder to approve.

Read the story →

Know of a data center project or vote we're missing? Email .

Data center news across Virginia, every Thursday.