Stafford approves Accokeek data center, larger Route 3 sites up next
Stafford supervisors approved a 590,000-square-foot data center campus 4-3, and the Planning Commission takes up four much larger Kings Highway sites on Oct. 14.
Stafford County supervisors approved the Accokeek Center data center campus 4-3 at a meeting that began the evening of Wednesday, Oct. 7. The rezoning allows two data center buildings of up to two stories, totaling 590,000 square feet, plus an electrical substation on 121 mostly vacant acres in the Falmouth District, between Interstate 95 and U.S. 1 north of Eskimo Hill Road.
Supervisors Deuntay Diggs, Maya Guy, Kecia Evans and Tinesha Allen voted yes. Crystal Vanuch, Darrell English and Pamela Yeung voted no. A motion by Vanuch to delay the vote to Oct. 20 so staff could produce net revenue figures failed 5-2. The applicant estimated $13 million to $15 million a year in revenue. That figure is gross, and the meeting produced no net figure.
Conditions attached to the rezoning include cooling with reuse water rather than drinking water or groundwater, at least 45 acres of preserved trees, a noise cap of 55 decibels at the project line. County utilities staff said about 90% of the reuse water system's capacity is now committed.
The next decision is much larger. The Stafford Planning Commission holds a public hearing on Wednesday, Oct. 14, at 6 p.m. on four data center sites along Kings Highway (Route 3) near the Rappahannock River: Forest Lane, Simms Farm, Sisson North and Sisson South, all in the George Washington District. The Forest Lane site alone covers about 850 acres.
Charles Payne, an attorney for the applicants, said full build-out of the Kings Highway sites would generate $245 million a year for the county, about 20% of its budget, and would include more than $80 million in county water infrastructure, with 55% of the land kept as open space. The commission's vote is a recommendation; the Board of Supervisors makes the final decision, and no date has been set.
With Loudoun and Prince William tightening their rules, Stafford is becoming one of the next fronts for data center growth in Northern Virginia, and the Route 3 sites are many times the size of the campus just approved.
What's next
- Oct. 14 Stafford Planning Commission public hearing on four Kings Highway data center sites, 6 p.m.
- TBD Board of Supervisors final decision on Kings Highway sites
Sources
- Potomac Local: Stafford supervisors approve Accokeek Center, 4-3
- Fredericksburg Free Press: Supervisors OK Accokeek campus
- WJLA: Stafford residents oppose data centers near Rappahannock
- FXBG Advance: Stafford data center hearings
- DCD: Forest Lane data center proposed on 850 acres
How we source: sources and corrections.
Related stories
Wythe zoning draft would shield data centers with county permits
Wythe County's draft Land Use Classification Ordinance would treat projects holding certain county permits as lawful, and a Board of Supervisors hearing is tentatively set for Dec. 3.
Read the story →Chesterfield returns Nov. 18 to data center car tax cut
Chesterfield's Board of Supervisors takes up, for the third time, an ordinance sending all data center tax revenue toward lower car taxes.
Read the story →Data center tax exemption is 60% of Virginia incentive spending
JLARC's 2026 incentives report puts the data center sales tax exemption at about $4.06 billion of $6.8 billion in incentive spending since fiscal 2016.
Read the story →Spot an error? Corrections and sourcing · Send a tip.